There may be a scenario where you have a 'master' board that aggregates all teams (within a project) work in progress. This may mean an item is appears across multiple boards, how does FlowViz handle this from a work item age perspective? |
Beta Was this translation helpful? Give feedback.
Answered by
nbrown02
Mar 16, 2022
Replies: 1 comment
-
Beta Was this translation helpful? Give feedback.
0 replies
Answer selected by
nbrown02
Sign up for free
to join this conversation on GitHub.
Already have an account?
Sign in to comment
Without any filters, the Work Item Age chart will show a dot for a work item multiple times on a chart if the item is present on more than one board.
If you filter via Team, then the chart will update to reflect the teams current Kanban board and items in progress, like so: